PCMS   MISTRAS NDT Services

PCMS Version 7.0

PCMS Version 7.0.

PCMS Version 7.0.

The following modules and enhancements have been added. Please visit the PCMS Product Overview page for more information.

New Modules
  • Import & export risk ranking, damage mechanisms & consequences for individual circuits
  • Add RBI Results tab to Circuit window to display RBI calculations
  • Sort & query circuits by risk ranking
  • Plot circuits in an RBI Matrix based upon risk ranking
  • Add inspection techniques and susceptible damage mechanisms to inspection schedules
  • Calculate due dates based on existing rules or RBI target dates
  • Capture inspection effectiveness on event reports
  • Build fluid properties per service
  • Identify equipment risk rank equal to worst acting circuit risk rank
  • Based upon API 571, API 580 & API 581
  • Developed with input from industry experts
  • Identify susceptible damage mechanisms per circuit
  • Identify consequences per circuit
  • Automatically create inspection plans identifying potential damage mechanisms & recommended inspection techniques
  • Plot results in a user configurable 5 x 5 matrix based upon risk ranking
  • Evergreen inspection results & continuous monitoring into the RBI Calculator

Enhancements
  • Support AutoCAD 2006, 2007, 2008, 2009 & 2010
  • Add System Builder window with Operating Parameters
  • Add underlined fields that affect RBI
  • Add Mass Update capability to circuit window
  • Add governing code per circuit to override equipment governing code
  • Split asset and service fields
  • Perform bundle swapping
  • Add sub-components
  • Add pipe segment/line component
  • Add number of tubes plugged
  • Sort all filtering fields alphabetically
  • Add support for NULL & NOT NULL operators
  • Allow user override of operators
  • Support Oracle 10g
  • Support SQL Server 2005
  • Add support for Excel and Access
  • Add schedules to window
  • Add RBI damage mechanism and consequences
  • Add MAWP & MAWT to protection grid
  • Make equipment group user configurable
  • Change window display setting to use equipment type rather than equipment group
  • Build SRD parts based upon SRD Style – not Equipment Type
  • Add special instructions and procedures to checklist templates
  • Add event template customization
  • Add summary grid to Format Builder for navigation and analysis
  • Streamline checklist interface
  • Add grouping capabilities to checklist
  • Redesign general and event report tab layout in event window
  • Capture inspection techniques used
  • Capture multiple indications
  • Identify repairs performed
  • Capture inspection effectiveness
  • Add class based calculations
  • Add TML inspection date calculations
  • Add RBI target date calculations
  • Offer option to use RBI or rule-based dates
  • Calculate due dates based upon event date, in-service date or plant start-up date
  • Eliminate half life interval calculation (half life date still used)
  • Create custom schedules per equipment (add and delete capability added to schedule window)
  • Create schedules automatically based upon event configuration settings
  • Event driver of schedule is optional
  • Equipment events may drive circuit & component schedules
  • Merge Recommendations into IWR window
  • Add IWR Type to distinguish Recommendations from IWRs
  • Make event optional when adding IWRs
  • Can add IWRs to equipment, events, schedules or event categories
  • Add support for blank Required Completion Dates
  • Add option to update PCMS with the SAP Revision number
  • Add Maintenance Work Center to the IWR Link
  • Add Notification Status to the IWR Link
  • Eliminate the need left-pad SAP values with zeros
  • Add an option to close IWRs when the Work Order is completed in SAP
  • Add SAP Functional Location to the IWR Summary tab
  • Prevent "read only" users from clearing certain data fields
  • Specify governing code at circuit level so that individual circuits may calculate t-min differently.  E.g. vessel trim may use B31.3
  • Make use of internal PCMS piping t-min table optional
  • Offer system default t-min table and material default tables
  • Add corrosion allowance calculation for pipe
  • Override circuit t-min calculation settings per TML
  • Show all t-min calculation results regardless of method selected
  • Add basis for manual t-min values
  • Add stress values from ASME code & associate with specific material
  • Calculate stress based upon material and design temperature
  • Show basis for stress calculation
  • Add option to use suggested rate until calculated average rate established
  • Change calculate order to Thickness, RBI then Inspect2
  • Set QA to "R"etired if reading EQUALS t-min
  • Add T/A Planning picklist to schedule
  • Associate schedule date with unit shutdown date
  • Mass schedule events for a turnaround
  • Added context sensitive help
  • Added new System View Navigator
  • Added IWR to main window and navigator tree
  • Enable more than one instance of PCMS to run
  • Multiple files can be selected in open dialog and attached in one step
Sitemap | Contact Us